Your Legal Solution Starts Today


Court of Appeal: A Contract Stated to Last 30 Years May Still Expire Earlier – Lessons on Renewal, Vacant Possession and Damages

Case Commentary: Vigilant Ventures Sdn Bhd v Lembaga Kemajuan Ikan Malaysia
Court of Appeal Malaysia | Civil Appeal No. K-01(NCVC)(W)-391-07/2023
Decision dated: 24 June 2026

A commercial agreement states that the parties intend for their relationship to last 30 years.

Does that necessarily give one party an enforceable right to continue the arrangement for the entire 30 years?

The Malaysian Court of Appeal’s decision in Vigilant Ventures Sdn Bhd v Lembaga Kemajuan Ikan Malaysia demonstrates why the answer depends on the precise wording of the contract.

The dispute involved approximately 128.82 hectares of land, a long-running aquaculture project, a Collaboration Agreement, a Tenancy Agreement, continued occupation after contractual expiry, allegations of fraudulent misrepresentation and more than RM2.57 million in damages awarded by the High Court.

The Court of Appeal ultimately affirmed that the agreements had expired and that vacant possession had to be delivered, but set aside the High Court’s awards of RM2.4 million in general damages and RM171,804.78 in special damages.

From our perspective at JY Ko Advocates & Solicitors, the case provides important guidance for businesses involved in long-term commercial arrangements, joint ventures, tenancy disputes and contractual litigation in Malaysia.

Background: 128.82 Hectares and an Aquaculture Project

Lembaga Kemajuan Ikan Malaysia (“LKIM”) was the registered proprietor of several parcels of land at Pantai Merdeka, Kedah measuring approximately 128.82 hectares.

The land was used for a fisheries and aquaculture project involving prawn farming, fish farming and a hatchery centre.

In 2006, Vigilant Ventures Sdn Bhd approached LKIM with proposals to take over and operate the project.

In its proposal, Vigilant Ventures represented, among other matters, that it possessed knowledge, capability and expertise in prawn and fish farming using high-technology systems.

It also represented that it had experts and entrepreneurs with experience in aquaculture and food processing, business and technology networks, and experienced management personnel capable of implementing the proposed programmes.

Following the proposal, LKIM offered to allow Vigilant Ventures to take over the project’s operations.

The parties subsequently entered into:

  1. a Collaboration Agreement dated 5 May 2008; and
  2. a Tenancy Agreement dated 20 February 2014.

These agreements eventually became the foundation of the litigation.

What Did the Collaboration Agreement Require?

Under the Collaboration Agreement, the parties agreed to collaborate in operating the prawn and fish farming and hatchery project.

LKIM was to provide basic infrastructure facilities on the land.

The agreement also imposed several significant obligations upon Vigilant Ventures.

No Assignment or Subletting

Clause 6.1(h) prohibited Vigilant Ventures from assigning, subletting, parting with possession of or sharing the occupation or use of the land or any part of it.

Training and Technology Transfer

Clause 9 required Vigilant Ventures to provide training and technology transfer to LKIM’s personnel, with the costs to be borne by Vigilant Ventures.

3% Profit Guarantee

Clause 10 provided for a profit guarantee based upon the gross sales value of marine produce sold and delivered.

Under the contractual arrangement:

  • 97% of the Gross Income would be retained by Vigilant Ventures;
  • 3% would be paid to LKIM; and
  • the payment was to be made within 30 days after submission of the approved audited accounts to the Companies Commission of Malaysia.

These provisions later became relevant to the allegations of breach and, importantly, to the Court’s consideration of damages.

The Critical Clause: Was This Actually a 30-Year Agreement?

Clause 4 was at the centre of the dispute.

The clause began by expressing the parties’ intention that the agreement would survive for 30 years, described as the “Lease Period”.

However, the clause then established a detailed mechanism governing the actual contractual duration.

The contractual periods were:

Trial Period: 5 May 2008 – 4 May 2011
First Extension: 5 May 2011 – 4 May 2014
Second Extension: 5 May 2014 – 4 May 2017
Future Extensions: After 4 May 2017, subject to mutual written agreement for subsequent three-year terms.

This distinction ultimately determined the dispute.

The Tenancy Agreement

The parties subsequently entered into the Tenancy Agreement dated 20 February 2014.

Interestingly, the agreement was expressed to operate retrospectively for three years from 5 May 2011 until 4 May 2014.

Vigilant Ventures was required to pay rent of RM400 per month for each hectare of land, payable annually from the date of possession.

The Tenancy Agreement itself was not renewed after 4 May 2014.

Nevertheless, LKIM permitted Vigilant Ventures to continue occupying the land during the second extension period of the Collaboration Agreement, which continued until 4 May 2017.

What Happened When 4 May 2017 Approached?

This chronology became particularly important.

On 31 January 2017, Vigilant Ventures applied to LKIM for an extension of the Tenancy Agreement beginning from 5 May 2017.

That application was not approved.

Nevertheless, after the second extension expired on 4 May 2017, Vigilant Ventures remained on the land and continued paying rent at the same monthly rate.

LKIM accepted those payments.

At first sight, continued occupation coupled with continued acceptance of rental might appear significant.

But the subsequent communications between the parties were crucial.

LKIM Found the Project in an Abandoned State

On 13 August 2017, LKIM conducted a site visit.

According to the grounds of judgment, the project was found to be in an abandoned state and not properly managed by Vigilant Ventures.

This resulted in a meeting of LKIM’s Aquaculture Projects Technical Committee.

On 5 October 2017, LKIM wrote to Vigilant Ventures informing it that:

  • the Tenancy Agreement and Collaboration Agreement had expired;
  • Vigilant Ventures could continue operating pending any new offer, provided rental continued to be paid; and
  • Vigilant Ventures was required to submit a new proposal paper for operation of the project.

This correspondence was important because it indicated that the continued occupation was not being treated as an automatic continuation of the previous contractual arrangement.

A New Proposal Was Eventually Rejected

Vigilant Ventures did not submit the new proposal within the stipulated time despite reminders.

The proposal was eventually submitted and presented on 27 February 2019.

During that presentation, Vigilant Ventures informed LKIM of the need to bring in new investors possessing modern aquaculture technology because local technology had become outdated.

On 2 May 2019, LKIM rejected the new proposal and gave Vigilant Ventures 30 days’ notice to deliver vacant possession.

Vigilant Ventures appealed against the decision on 10 May 2019, but the appeal was rejected.

LKIM subsequently issued a Notice of Demand dated 24 February 2020, demanding outstanding rental and vacant possession.

Vigilant Ventures did not comply.

Litigation followed.

LKIM’s Claim Against Vigilant Ventures

LKIM commenced proceedings in June 2020.

Its claims included declarations concerning the expiry of the agreements, an injunction preventing third parties from operating on the land, vacant possession and various categories of damages.

Among other relief, LKIM sought:

  • general damages arising from alleged negligence and failure to implement the project;
  • damages arising from alleged fraud and misrepresentation;
  • damages for failure to achieve the represented production capacity;
  • damages for loss of the right to enjoy and develop the land;
  • RM171,804.78 in alleged lost guaranteed profits for 2014–2019;
  • outstanding rental of RM37,640.55;
  • exemplary damages;
  • interest; and
  • costs.

Vigilant Ventures denied the claims.

Vigilant Ventures Said the Agreement Continued Until 2038

Vigilant Ventures’ central position was that the Collaboration Agreement was intended to last for 30 years until 2038.

It maintained that it had successfully completed the Trial Period and that LKIM’s subsequent conduct demonstrated satisfaction with its performance.

It also asserted that it had spent substantial sums rehabilitating and improving the site and that LKIM knew about and consented to its collaboration with third parties.

Vigilant Ventures further alleged that LKIM itself had failed to comply with contractual obligations, including obligations concerning infrastructure, formation of a Management Committee and provision of a new agreement.

By counterclaim, Vigilant Ventures sought, among other relief, a declaration that the Collaboration Agreement remained effective until 4 May 2038 and an order permitting it to continue operating the project until then.

The commercial consequences were therefore substantial.

This was not merely an argument about historical breaches. It concerned whether Vigilant Ventures had the right to continue occupying and operating on approximately 128.82 hectares of land for many more years.

High Court: Agreements Expired and RM2.57 Million in Damages Awarded

After a full trial involving three witnesses for LKIM and two witnesses for Vigilant Ventures, the High Court substantially allowed LKIM’s claim and dismissed Vigilant Ventures’ counterclaim.

The High Court:

  • declared that the agreements had expired and were no longer binding;
  • ordered vacant possession;
  • awarded RM2.4 million in global general damages;
  • awarded RM171,804.78 in special damages for loss of guaranteed profits;
  • dismissed the exemplary damages claim;
  • dismissed the outstanding rental claim; and
  • dismissed Vigilant Ventures’ counterclaim with costs of RM30,000.

Vigilant Ventures appealed.

Court of Appeal: The 30-Year Intention Was Subject to the Renewal Mechanism

The Court of Appeal examined Clause 4 closely.

Although the parties had expressed an intention for the arrangement to survive for 30 years, the Court held that this intention was expressly subject to the detailed contractual mechanism governing the Trial Period and subsequent extensions.

The first and second extensions were automatic.

Future extensions were different.

After the second extension expired, any future extension had to be:

“mutually agreed upon by the parties in writing”.

The Court considered this difference in drafting significant.

If the parties intended the subsequent extensions to be automatic, they could have used the same expression—“automatic extension”—that appeared in relation to the earlier extensions.

They did not.

Accordingly, neither party possessed a unilateral contractual right to compel an extension beyond 4 May 2017.

Even Vigilant Ventures’ Own Witness Accepted That Written Agreement Was Required

One particularly significant evidential point arose during cross-examination.

Vigilant Ventures’ own witness accepted that once the second extension ended, mutual written agreement was required for the project to continue.

The Court noted that this evidence was neither challenged nor contradicted during re-examination.

No such mutual written agreement was subsequently reached.

The Court therefore affirmed that the Collaboration Agreement expired on 4 May 2017 by effluxion of time.

Our View: The “30 Years” Wording Did Not Override the Machinery of the Contract

This is one of the most useful lessons from the judgment for Malaysian businesses.

Commercial parties sometimes focus on the headline proposition contained in an agreement:

“30-year collaboration.”

“10-year tenancy.”

“Renewable for another five years.”

But the real legal question may be:

How does the contract say that subsequent period comes into existence?

An intention to maintain a relationship for 30 years is materially different from an unconditional contractual right to insist upon 30 years.

The renewal machinery matters.

Terms such as “automatic extension”, “option to renew”, “subject to mutual agreement”, “subject to satisfactory performance”, “upon written request” and “mutually agreed in writing” should therefore be drafted and reviewed carefully.

Expiry and Termination Are Not the Same Thing

Vigilant Ventures also argued that LKIM had not issued the necessary contractual notice of default or termination.

But the Court of Appeal drew an important distinction.

The Court held that the Collaboration Agreement had expired by effluxion of time.

It had not been brought to an end through contractual termination for breach.

Accordingly, the contractual provisions governing termination for breach—including notice and cure requirements—were irrelevant to the issue of expiry.

No termination notice was required to make an already-expired agreement expire.

This distinction can be decisive in contractual litigation.

Fraudulent Misrepresentation Was a Separate Issue

The High Court had also found fraud and misrepresentation concerning representations made by Vigilant Ventures regarding its expertise, experience and networks.

Among the matters identified in the High Court’s findings were that Vigilant Ventures allegedly lacked the represented expertise and had engaged a third party to implement the project without LKIM’s consent.

The High Court also referred to certain companies identified as business partners in the original proposal which were found not to exist.

The Court of Appeal nevertheless carefully separated the misrepresentation issue from the contractual expiry issue.

It explained that a contract induced by fraud remains valid until rescinded.

The finding of fraud was therefore relevant to the damages question, whereas the expiry of the agreement arose independently through Clause 4.

The RM171,804.78 Special Damages Award Was Set Aside

Although LKIM succeeded on expiry and vacant possession, it did not retain the damages awarded by the High Court.

The High Court had awarded RM171,804.78 in special damages for the alleged loss of the 3% guaranteed profit for 2014–2019.

The Court of Appeal emphasised that special damages must be strictly proved.

LKIM bore the burden of establishing the actual gross income and therefore the 3% allegedly payable.

However, the Court found that there was no documentary evidence establishing Vigilant Ventures’ relevant sales.

Without strict proof, the award could not stand.

The entire RM171,804.78 special damages award was therefore set aside.

The RM2.4 Million General Damages Award Was Also Set Aside

The High Court’s RM2.4 million global general damages award also encountered difficulties.

The Court of Appeal identified several issues.

First, LKIM had not pleaded a claim for an account of profits or unjust enrichment.

Second, Clause 10 only entitled LKIM to 3% of gross income from marine produce. It did not give LKIM an entitlement to payments received by Vigilant Ventures through third-party collaborations.

Third, LKIM had not sufficiently proven an actual loss directly caused by the alleged misrepresentation.

The Court also observed that, following the finding of fraudulent misrepresentation, LKIM could have pursued remedies such as rescission and restitution or affirmation of the contract coupled with damages for deceit.

Instead, the general damages claim before the Court was advanced on an insufficiently particularised basis.

The RM2.4 million award was therefore set aside.

Winning on Liability Does Not Mean Winning on Quantum

This is another important lesson from the case.

LKIM successfully established that the contractual arrangement had expired.

It obtained vacant possession.

Vigilant Ventures’ counterclaim seeking the right to continue until 2038 failed.

Yet more than RM2.57 million in damages awarded by the High Court disappeared on appeal because the legal and evidential foundation for those damages was insufficient.

From a litigation perspective, liability and quantum must therefore be approached as separate exercises.

A claimant should ask from the beginning:

What is our precise cause of action?

What remedy flows from it?

What losses are legally recoverable?

Have those losses been specifically pleaded where necessary?

Can each component be proved through contemporaneous documents, accounts, invoices, receipts, expert evidence or other admissible evidence?

A strong case on liability cannot substitute for deficient proof of damages.

Vacant Possession Was Ultimately Affirmed

Having concluded that the Collaboration Agreement expired on 4 May 2017 and had never been renewed through mutual written agreement, the Court held that Vigilant Ventures had no contractual foundation for remaining in possession.

Its counterclaim therefore failed.

The Court affirmed the vacant possession order and required Vigilant Ventures to deliver possession within 60 days from the date of judgment, failing which LKIM could enter and take possession.

Final Outcome

The appeal therefore produced a split result.

The Court of Appeal affirmed:

  • the expiry of the Collaboration Agreement;
  • the expiry of the Tenancy Agreement;
  • LKIM’s entitlement to vacant possession; and
  • dismissal of Vigilant Ventures’ counterclaim.

However, it set aside:

Each party was ordered to bear its own costs in the Court of Appeal and below.

What Malaysian Businesses Can Learn From This Decision

In our view at JY Ko Advocates & Solicitors, Vigilant Ventures v Lembaga Kemajuan Ikan Malaysia illustrates several important principles for commercial contracting and litigation.

First, read the entire duration clause. A stated intention for a 30-year relationship does not necessarily create an unconditional 30-year contractual right.

Second, renewal mechanisms matter. An automatic renewal is fundamentally different from a renewal requiring mutual written agreement.

Third, distinguish expiry from termination. Notice and cure provisions applicable to termination for breach may not apply where a contract simply expires by effluxion of time.

Fourth, document post-expiry arrangements. If parties continue doing business after an agreement expires, their legal relationship should be clarified rather than left to assumption.

Fifth, plead the appropriate remedy. Damages, restitution, rescission, unjust enrichment and an account of profits are not interchangeable remedies.

Sixth, preserve documentary evidence of loss. A damages claim should ideally be built from the underlying financial and documentary evidence rather than reconstructed only when litigation begins.

Finally, contractual litigation is often won or lost on drafting. A few words governing renewal, notice, termination or entitlement can determine rights worth millions of ringgit.

JY Ko Advocates & Solicitors – Contractual and Commercial Disputes

Commercial disputes are rarely limited to the simple question of whether somebody breached a contract.

They frequently require consideration of contract interpretation, expiry and renewal, termination rights, misrepresentation, occupation and possession, damages, evidential requirements and the remedies actually available under Malaysian law.

At JY Ko Advocates & Solicitors, we advise and represent individuals, business owners and companies in contractual and commercial disputes, including:

Our approach is to examine both the immediate dispute and the underlying contractual architecture: what rights were actually created, whether those rights remain enforceable, how the agreement may be brought to an end, and what remedies can realistically be pursued and proven.

Where a dispute concerns substantial commercial rights, long-term occupation of property or significant monetary exposure, early legal review can be particularly important.

Written on: 20th September 2026, Sunday


Contact JY Ko Advocates & Solicitors to make an appointment today!

🌐 Call us: +6017.6965.966 (Call / WhatsApp)

📩 Email Us: nick@jykolaw.com

Disclaimer: The above proposition is subject to actual facts and circumstances and shall never be referred as the actual law without seeking legal advice. Consult us for more information!